Concrete slab · 12x12
How Much Concrete for a 12x12 Slab?
A 12' × 12' slab 4" thick is 48.0 cu ft of concrete, 1.78 cubic yards: 80 bags of 80 lb mix or 107 bags of 60 lb. With 5% extra for spillage and uneven ground, buy 84 bags of 80 lb, or order 2 cu yd of ready-mix.
Open this 12x12 slab in the 3D calculator
Concrete for a 12x12 slab by thickness
| Thickness | Cubic feet | Cubic yards | 80 lb bags | 60 lb bags | Buy (80 lb, +5%) | Ready-mix (+5%) |
|---|---|---|---|---|---|---|
| 3-1/2" | 42.0 | 1.56 | 70 | 94 | 74 | 1.75 cu yd |
| 4" | 48.0 | 1.78 | 80 | 107 | 84 | 2 cu yd |
| 5" | 60.0 | 2.22 | 100 | 134 | 105 | 2.5 cu yd |
| 6" | 72.0 | 2.67 | 120 | 160 | 126 | 3 cu yd |
An 80 lb bag makes 0.6 cu ft and a 60 lb bag 0.45 cu ft (QUIKRETE). Ready-mix is ordered by the quarter yard. Patios and walks are usually 4" thick; a slab for a car or a hot tub, 5" to 6".
Everything else for a 12x12 slab
- Gravel base: 3 tons of crushed stone for a 4" compacted base (20% added for compaction).
- Rebar: 18 sticks of #3 rebar, 20' long, for a grid 18" apart each way, 16 chairs to hold it at mid-depth, and a roll of tie wire.
- Forms: 2x6 boards around the edge (2 × 16', 2 × 12') and 22 stakes.
- Control joints: 4 panels of 6' × 6', cut 1" deep.
Shopping list and cost
| Item | Quantity | Cost |
|---|---|---|
| Concrete mix, 80 lb bags | 84 bags | $502 |
| Gravel base (crushed stone, 3/4" minus) | 3 tons (2.13 cu yd) | — |
| #3 rebar, 20' sticks | 18 sticks | $136 |
| Rebar chairs | 16 chairs | $14 |
| Rebar tie wire | 1 roll | $18 |
| 2x6 form boards, 16' | 2 boards | $39 |
| 2x6 form boards, 12' | 2 boards | $30 |
| Wood stakes, 18" | 22 stakes | $11 |
| Estimated total (7 of 8 items priced) | $751 | |
Questions about a 12x12 slab
How many 80 lb bags of concrete for a 12x12 slab?
80 bags at 4" thick, since an 80 lb bag makes 0.6 cu ft. Add 5% for spillage and a base that is not perfectly flat: 84 bags. At 6" thick it is 126 bags with the same extra.
How many yards of concrete for a 12x12 slab?
1.78 cubic yards at 4" thick. Ready-mix is ordered by the quarter yard, so with 5% extra order 2 cu yd. At 5" it is 2.5 cu yd and at 6" 3 cu yd.
Bags or a ready-mix truck for a 12x12 slab?
84 bags is 1.87 yards of mixing by hand. Past about a yard, a ready-mix truck usually costs less and pours the slab in one go, with no cold joints; ask the plant about its minimum load.
What does a 12x12 concrete slab cost in materials?
About $751 for everything on the shopping list that has a store price (one US home center, Nov 18–22, 2026). The gravel base (3 tons) is bought by the ton from a local yard and is not in that figure, nor are tools, delivery and labor.